Arizona Subcontractor
Indemnity Exposure Clarified
The MT Builders
decision reminds subcontractors to review construction contracts for land mines
that go off when charges of construction defects are made
A November 2008 Arizona
Court of Appeals decision (in
MT Builders v. Fisher Roofing) provides a guide for writing a narrow
indemnity clause that limits the subcontractor’s liability for injuries or
defects on a construction job. More important, it reminds subcontractors to have
legal and insurance professionals review subcontracts for “land mines” that go
off when charges of construction defects are made.
Background. In
January 2001, an Arizona condominium association filed a construction defect
lawsuit against a number of defendants, including the general contractor (MT
Builders), the roofing subcontractor (Fishing Roofing), and other
subcontractors.
MT Builders filed a
cross-claim against the subcontractors, to force them to indemnify MT against
any losses MT may incur in the lawsuit. Its cross-claim was based on the
indemnity provision in MT’s standard subcontract agreement that it had used with
all of its subs. The “narrow form” indemnity clause provided:
To the fullest extent
permitted by law, the Subcontractor shall indemnify and hold harmless
the Owner, Architect and the Builder and all their agents and employees from
and against all claims, damages, losses and expenses, including but not
limited to attorney’s fees and court costs, arising out of or resulting from
the performance or non- performance of the Subcontractor’s Work under this
Subcontract ... to the extent caused in whole or in part by any negligent
act or omission of the Subcontractor or anyone directly or indirectly
employed by him or anyone for whose acts he may be liable[.] (Emphasis
added)
In late 2002, MT Builders
and most of the subcontractors settled the association’s lawsuit for $1.75
million. Three subcontractors, including Fisher Roofing, refused to participate
in the settlement, and the association assigned to MT its claims against them.
Thus, the lawsuit continued among MT, Fisher and the other holdout subs.
In 2004, MT filed a
motion for summary judgment asking that Fisher be ordered to reimburse MT for
Fisher’s share of the $1.75 million settlement and for MT’s attorneys’ fees. MT
argued that the $240,500 that the association had spent on roof repairs in 2004
was the best evidence of Fisher’s fair share of the damages, and that Fisher had
no right to contest MT’s settlement with the association because Fisher had
refused to participate.
Fisher countered that
deciding the extent of its negligence, if any, required a trial. Fisher argued
that:
-
MT must prove that
Fisher was negligent;
-
if MT met that
burden, MT must then prove how much damage Fisher’s negligence caused; and
-
because of
conflicting evidence, Arizona law did not allow the superior court to enter
judgment without hearing all of the evidence at trial.
The court granted MT’s
motion, awarding summary judgment against Fisher for $240,500, plus $113,000 of
MT’s attorneys’ fees.
Appeal and Remand.
Fisher appealed the superior court’s decision and found a more receptive
audience at the Arizona Court of Appeals. The appellate court held that, given
the language of the indemnity clause, the trial court should not have granted
summary judgment and that a trial would be required to determine the extent of
Fisher’s fault.
The case was remanded,
and the trial court was instructed to resolve conflicting testimony as to (a)
whether Fisher’s work was negligent, and (b) to what extent its negligence had
caused damage, rather than simply accepting the $240,500 figure that the
association spent on repairs. The court could not presume that all roof repairs
were Fisher’s responsibility if, for example, there was evidence that the HVAC
sub had damaged the roof. In short, MT was entitled to indemnity only “to the
extent” of Fisher’s fault, and it was MT’s burden to prove the degree of
Fisher’s fault.
In addition, the trial
court was instructed to require MT:
-
as a prerequisite for
obtaining indemnity from Fisher, to prove that its overall settlement was
reasonable and prudent, given the risk of exposure at trial and the strength
of the available defenses; and
-
to show how much of
the settlement amount was attributable to Fisher’s fault and that its
settlement of the Fisher claims also met the “reasonable and prudent” test.
On the last point, the
court noted, “Even if the overall settlement reached by MT Builders with the
Association was reasonable and prudent under the circumstances, to obtain
indemnity from Fisher, MT Builders was required to show that its settlement of
the Fisher-based claims met this test.”
Lessons Learned.
For Arizona subcontractors, the MT Builders decision provides detailed
instruction on how a trial court must treat a carefully written, narrow form
indemnity clause. The decision holds that the words “to the extent caused by the
negligent act of the subcontractor” can significantly reduce a subcontractor’s
exposure.
In addition, MT
Builders may turn out to influence “additional-insured” endorsements
required by form subcontracts. Since November 2008, when the decision was
issued, some liability insurers have begun to write the same type of “to the
extent of” language into additional-insured endorsements to restrict the
insurer’s liability to the extent of subcontractor negligence only. (See your
insurance agent for more information.)
MT Builders
provides new, useful instruction in crafting an indemnity clause and should
remind all contractors and subcontractors to understand the indemnity provisions
of their contracts and to be sure that their insurance covers their exposure.
Subscribe
|
Article Index |