Construction Law
|
 |
Architect's Errors May Create Liability for a
Contractor's Damages
The Arizona Court of Appeals rules that a
contractor may sue a design professional for breach of implied warranty even if
there is no contract between the two parties
Kent Lang
|
| |
|
In the
early 2000s, Vern Haugen owned a mountainside residential lot in Scottsdale. He
also owned a construction company, North Peak Construction, LLC. Haugen planned
to build on the lot a home situated in such a way that its residents could enjoy
an attractive view of the city. He hired an architectural firm, Architecture
Plus, Ltd., to design the home.
The
contract required Architecture Plus, in designing the home, to consider Haugen’s
requirements. In addition to discussing with Architecture Plus the importance of
properly orienting the home to take advantage of the view, Haugen gave
Architecture Plus a topographical map and marked the “limited view corridor”
within which the home was to be designed and aligned.
Shortly
thereafter, Haugen sold the lot and the preliminary architectural plans, and the
buyer separately contracted with Architecture Plus. That contract contained the
same terms as the original contract, plus some provisions for design
alterations. The final construction plans for the home were signed and sealed by
the architect. The buyer contracted with Haugen’s company, North Peak
Construction, to the build the home.
In 2006,
after construction began, North Peak discovered that the architect’s plans
aligned the home so that, rather than overlooking the city, it faced a mountain
and a water tank. North Peak demolished the work it had already performed and
rebuilt the home, incurring nearly $165,000 in additional expenses.
Lawsuit. In 2009, North Peak sued
Architecture Plus and the architect personally for breach of implied warranty
and for negligence. In its complaint, North Peak also requested payment of its
attorneys’ fees, per A.R.S. § 12-341.01(A), claiming that its implied warranty
claim arose out of contract.
In
response, Architecture Plus sought to dismiss the breach of implied warranty
claim on the basis that North Peak’s real claim was for negligence and that
there was “no contractually-based claim for breach of implied warranty insofar
as design professionals are concerned.” Architecture Plus argued that, in
essence, North Peak’s implied warranty claim was a back-door attempt to “convert
an action for which attorneys’ fees are not recoverable
into one in which attorneys’ fees are recoverable”
[emphasis added].
The
Superior Court judge agreed with Architecture Plus and dismissed North Peak’s
implied warranty claim, noting that North Peak’s professional negligence claim
was based in tort, not in contract, and thus not eligible for recovery of
attorneys’ fees.
Architecture Plus then asked the court to dismiss North Peak’s negligence claim,
arguing that the statute of limitations had run out. The judge granted that
motion, too, and dismissed North Peak’s entire claim.
North
Peak appealed the dismissal of its claim for breach of implied warranty. The
Arizona Court of Appeals found North Peak’s claim against Architecture Plus to
be valid and sent the case back for trial in Superior Court. (Read the court's
opinion in North
Peak Construction, LLC v. Architecture Plus, Ltd.)
Legal
Reasoning. In considering North
Peak’s appeal, the Court of Appeals agreed with Architecture Plus that North
Peak had no contract-based claim for breach of implied warranty.
However,
the court relied on the Arizona Supreme Court’s 1984 opinion in Donnelly
Constr. Co. v. Oberg/Hunt/Gilleland, which provided that a claim for breach
of an implied warranty may be brought against a design professional even in the
absence of “privity,” i.e., when there is no written contract between the
parties, which was the case with North Peak and Architecture Plus.
In Donnelly,
the Supreme Court held that a contractor does not need to be in privity with an
architect in order to sue the architect for negligence and breach of implied
warranty, and the Court of Appeals applied that conclusion in North
Peak.
“Because Donnelly recognizes
that breach of an implied warranty is a valid cause of action against a design
professional and can be brought in addition to a claim of negligence,” wrote the
Court of Appeals in its opinion, “we must conclude that the [trial] court erred
in dismissing North Peak’s implied warranty claim.”
The Court
of Appeals also cited the Arizona Supreme Court’s 2008 ruling in The
Lofts at Fillmore v. Reliance Commercial Construction (see
related article), which concluded that “a claim for breach of an implied
warranty of habitability and workmanlike performance sounds in contract rather
than tort.”
Personal Liability. The Court of
Appeals also found that, if North Peak prevailed in Superior Court, the
architect could bear personal liability for North Peak’s claim for breach of
implied warranty.
“North
Peak’s implied warranty is not based on [the buyer’s] contract with Architecture
Plus, Ltd.,” wrote the Court. “Rather, the implied warranty is based on (1)
North Peak’s alleged reliance on the architectural plans and specifications, (2)
Donnelly’s recognition that ‘design professionals’ warrant ‘that they have
exercised their skills with care and diligence and in a reasonable,
non-negligent manner,’ and (3) the alleged signing and sealing by [the
architect] of the plans and specifications.”
Conclusion. For contractors and
design professionals, the main lesson in North
Peak is this: If a design
professional’s error causes a contractor to suffer damages, the contractor may
sue the design professional for breach of implied warranty even if there is no
contract between the two parties. |